Reduce and understand your energy consumption with SMART ENERGY
Case studies
11 April 2024
Number of project hours: 340H
Project Duration: 6 months
Our client is a truck engine manufacturer. They need to ensure the maintainability of the equipment fleet in their 11L engine manufacturing plant for the next 5 years. However, their equipment is aging. Therefore, our client aims to refurbish their drive system and wishes to have technical assistance for equipment monitoring.
We conduct an audit to determine the solutions to be implemented:
Based on these analyses and diagnostics, we then propose a maintenance plan to our client.