Retrofitting of the robotics part of a nine-colour printing line
Client expectation
A manufacturer specialising in plastic food wrapping chose to invest in a retrofitting of their nine-colour rotational printing line. The overall obsolescence of the robotics part led our client to re-think the machine system, replacing it with new equipment.
The aims were clear:
- Compensate for the obsolescence of the machine equipment
- Facilitate maintenance on the robotics.
DV GROUP solution
In order to reach these objectives, we proposed our client should replace all the robots on the line in the Siemens S5 range by the S7-1500 range. This replacement also included the transfer of API programmes and the machine network communication protocol, as well as the replacement of the IHM supervisor and the IHMs on the colour groups. Consequently, the experts in our design office were busy for several weeks in order to carry out this retrofitting project and comply with the programmed immobilisation time for this machine, in other words, two weeks.

Word carried out
DV GROUP technical solution:
- Verification of the current equipment configuration in order to define the new one.
- Full back-up of the machine
- Study of communication exchanges between robots
- Preparation work for the implementation of a communications gateway between the new and old equipment
- Approval of the platform
- Switch-over of the APIs onto the machine in several phases in order to diminish stoppage time
- Conversion work on the robot and display unit programmes, drawing of electrical diagrams, supply of equipment.
Following observation of a communication problem, we decided with our client to retrofit the entire machine in one single 15-day stoppage in order to carry out the work (instead of dealing with one printing group per month over 2 stoppage days).
- Full approval with acceptance of the communications platform
- Carrying-out of the work
- Commissioning
- Production assistance.
In the end, the 10 experts in our design office finished the site and commissioning in 12 days, in other words, three days fewer than had initially been scheduled.
Expertisen
Wir bieten Ihnen Lösungen in den Bereichen Engineering, Maintenance und Control, die mit der Kenntnis Ihrer Prozesse verbunden sind.
Fallstudien
Das könnte Sie interessieren

Preventive maintenance for 17 Siemens servomotors and drives

X-FAB : Replacement of two extractor fans

Troubleshooting of an induced draught fan

19 50 kg (2.2 kW) to 5 ton (7.2MW) motor/reducer/ventilator assemblies

Overhaul of an extruder reducer with 2 indexed output shafts

Modelling of the HTA/BT electric network

Projekt zur Verbesserung der Wartungsmethoden

Motorisation of compressors in a colliery gas compression station

Obsolescence of the oven’s 7 CC ALSTHOM drives

Retrofitting of an impressive balancing bench

Retrofit of a machine for superfinishing machined parts

Modification of the ride “Tonnerre 2 Zeus” [Zeus’ Thunder]

Präventivmaßnahmen an 2 Masterdrives (800 kW, Schrank mit 3 Türen)

Notfallreparatur eines Extrudermotors (200 kW) nach einer Schwingungsmessung

Plan zur vorbeugenden Wartung von Large Drive-Antrieben

Schwingungsüberwachung einer Kaffeeproduktionsanlage

Obsoleszenzmanagement: Prüfung des Materialbestands einer Fabrik für LKW-Motoren

Reparatur und Zuverlässigkeit von Antrieben

ELOPAK: Korrigierende vorbeugende elektronische Wartung

Präventive Maintenance von Siemens Masterdrive

Sicherstellung der Zuverlässigkeit von 32 Siemens (6SE70) Masterdrives in einer Papierfabrik

MELEGHY: Präventivwartung von 24 Siemens Powerblocks-Antrieben

Preventive maintenance contract

Emergency repair on a 120KW ABB ACS800 drive

2 LEROY SOMER 600 kW variators

Overhaul of 12 Siemens Torque Simotics T-1FW3 motors

Preventive maintenance for 17 Siemens servomotors and drives

X-FAB : Replacement of two extractor fans

Troubleshooting of an induced draught fan

19 50 kg (2.2 kW) to 5 ton (7.2MW) motor/reducer/ventilator assemblies

Overhaul of an extruder reducer with 2 indexed output shafts

Modelling of the HTA/BT electric network

Projekt zur Verbesserung der Wartungsmethoden

Motorisation of compressors in a colliery gas compression station

Obsolescence of the oven’s 7 CC ALSTHOM drives

Retrofitting of an impressive balancing bench

Retrofit of a machine for superfinishing machined parts

Modification of the ride “Tonnerre 2 Zeus” [Zeus’ Thunder]

Präventivmaßnahmen an 2 Masterdrives (800 kW, Schrank mit 3 Türen)

Notfallreparatur eines Extrudermotors (200 kW) nach einer Schwingungsmessung

Plan zur vorbeugenden Wartung von Large Drive-Antrieben

Schwingungsüberwachung einer Kaffeeproduktionsanlage

Obsoleszenzmanagement: Prüfung des Materialbestands einer Fabrik für LKW-Motoren

Reparatur und Zuverlässigkeit von Antrieben

ELOPAK: Korrigierende vorbeugende elektronische Wartung

Präventive Maintenance von Siemens Masterdrive

Sicherstellung der Zuverlässigkeit von 32 Siemens (6SE70) Masterdrives in einer Papierfabrik

MELEGHY: Präventivwartung von 24 Siemens Powerblocks-Antrieben

Preventive maintenance contract

Emergency repair on a 120KW ABB ACS800 drive